Introduction
The client operates a major petrochemical complex in southern Italy, equipped with multiple distillation columns and reaction units. The existing power distribution system was aging, frequently unstable, and lacked intelligent monitoring features. With the expansion of new process units, the client required a complete upgrade of the 10kV medium voltage electrical system to ensure safe and efficient plant operations.
- Location:
- Southern Italy
- Project Year:
- 2024
- Client Type:
- Petrochemical Manufacturer
- Solution Provided:
-
Supplied two 2500kVA dry-type transformers with enhanced thermal and moisture resistance
Installed our KYN28-12 medium voltage switchgear with Siemens VCBs for maximum reliability
Integrated online power quality monitoring and an energy management system
Enabled seamless integration with the client’s DCS system for remote control and data logging
Full CE certification and successful trial run under full-load operation
- Project Outcome:
- The upgraded distribution system now operates with high stability, meeting the continuous high-demand requirements of the petrochemical process. The client reported a noticeable improvement in power factor, a 40% reduction in voltage fluctuations, and over 60% improvement in maintenance efficiency. The entire project was completed in just 35 days, demonstrating ABILKEEN’s speed and expertise in delivering power solutions to the oil & gas sector.
Other Cases
Support Center
-
Download Center
Get the latest product datasheets, technical drawings, PDU configurations, and safety certificates tailored for data center & commercial building environments.View Now -
FAQ
Explore answers to common questions about load redundancy, power path design, transformer selection, and remote monitoring systems. Fast answers from our engineers.View FAQ -
Contact Support
Have a project with unique space, redundancy, or monitoring needs? Our technical team is ready to help design and optimize your system.Get Support